Wednesday, 1 August 2012

Site Visit 01.08.12

Existing glazing removed- new panels added to slopes

Electrics made safe- awaiting rooflights for reuse of conduits

Vertical panel to be fitted following completion of gutter insulation

Existing roof structure cleat retained as discussed


Bright white enamel finish of panel above/ liner of retained gutter below.

Excessive mastic to joint- to be trimmed

Roof structure cleat

Punkah fans set advise for possible client reuse elsewhere

RL panels primed awaiting Sarna membrane

Outlet plate to be removed/ enlarged

Felt back Sarna membrane on site

Bay 2 underway- existing plygene line still in place to Bay 3

Sarna installed to slope and taped back awaiting installation into well of gutter
All pipes/ penetrations to be retained to solid roof bays
Penetrations to sloped roof adjacent are failing- see pooling- also leaks below

Leaks to 1FL where penetrations/ waterproofing have failed. CR to price for replacing

See note above