Thursday, 9 August 2012

Site visit 08.08.12


Sarna membrane completed to 1 No. bay


Sarna cut around new outlet- additional strip to be installed as ball guard


4No. bays now fitted with metal panels


slope and vertical panels installed


Sarna tread on site for installation as part of roof access. Ladder details to follow


1st Velux rooflight installed. Power to be redisributed to head of rooflight- tbc.


Bilko access hatch on site


1st rooflight at roof level- insulation/ Sarna and cover flashings to follow