Sarna plast flashing completed to bay 1- awaiting mastic seal

Vertical panels to 3 & 4 awaiting Sarna

Vertical metal panel only remaining area requiring panel installation

Plygene gutter still remains to bay 4- awaiting gutter insulation/ membrane

2 No. velux rooflights required to complete installation to bay 1

All metal slopes now complete to roof

CB advises that exposed thread of fixings can be tapped off- impact will be minimised further when redecoration is carried out in phase II of works

10 No. velux rooflights now installed.
Flashing completed to centre rooflight (in image) with exception of 1 side following completion of electrics

14 No. remain to be installed

All metal panels installed to slopes. Sarna membrane installed to 3 No. slopes of 5.